The The following is an anticipated schedule for continued facilities discussions:
October 18: Board of Commissioners meeting (7:30pm, hybrid) – review of public comment to date and brief presentation of the Facilities Report, which will be released following the meeting for public review and comment. The report will provide a compilation of the research that went into the July 26, 2023 presentation.
October 25: Public Budget Workshop (4:00pm, Zoom) – public budget meeting where, among other things, the Board of Commissioners will discuss future financing plans for the Township.
November 16: Special Meeting of the Board of Commissioners (7:30pm, Zoom) – to hear public input on the proposed concepts and report and deliberate on the concepts. on May 16, 2022.



 

Detailed presentation  by architects of prospective  plans for all facilities.

View the presentation video.




 

GLENSIDE  COMMUNITY FACILITIES INFORMAL POP UP LISTENING SESSION VIA ZOOM

THURSDAY, AUGUST 11 



View the session at

https://www.youtube.com/watch?v=qyFDT4jpskM&list=PLwJOvBniQseMiL_VaD4XJEvC2S3J5Qy-3&index=3


ROWLAND COMMUNITY CENTER/EAST CHELTENHAM LIBRARY INFORMAL POP UP LISTENING SESSION VIA ZOOM

TUESDAY, AUGUST 9



View the session at

https://www.youtube.com/watch?v=SAp3kpP9NAE&list=PLwJOvBniQseMiL_VaD4XJEvC2S3J5Qy-3&index=4



 

KCBA and Re:Vision Architects  Hired to Evaluate Township Facilities and Facilitate Plan

The last Facilities Committee Meeting occurred on May 16, 2022.

View the video.


 

Facilities Informal Pop Up Listening  Sessions

July/August 2022


 LAMOTT COMMUNITY CENTER INFORMAL POP UP LISTENING CENTER VIA ZOOM

WEDNESDAY, JULY 27



View the session at https://www.youtube.com/watch?v=Ab4THVfDeFg&list=PLwJOvBniQseMiL_VaD4XJEvC2S3J5Qy-3&index=5



 

July 26 2023 Facilities

Study Presentation

May 16 Facilities

Committee Meeting

In June of 2022 the Township hired KCBA /RE:Vision to do a "space needs assessment" on all current facilities and to facilitate a process to plan for the future. They began work in early July familiarizing themselves with the facilities.
 
A  community engagement plan was implemented. A survey, that was part of the initial plan has not been implemented at this time. 


View their presentation at 1:04:30 of the June PW Committee Meeting.
 

As part of a larger plan to evaluate current facilities, the Township conducted three informal ”POP-UP LISTENING SESSIONS" for concerned residents. Architects from KCBA and RE:Vision facilitated these sessions.

October/November 2023 Public Meetings  